With construction just completed at Magnolia Residences, buyers are excited to be able to move into their brand new luxury over-sized apartments. Set to welcome its first residents this coming Tuesday, Magnolia Residences is the second installment in the $100million masterplanned community “Summerlin”, a boutique collection of just 27 two and three bedroom luxury apartments…
Magnolia Residences, Summerlin Banyo – April Construction Update – 2020
APRIL 2020 We are pleased to announce that since our last update the following milestones were achieved: Magnolia Residences • Construction complete and the plans are lodged with the local Council for plan sealing • Security system is being installed including CCTV to common areas • Final touches to landscaping are being done • We…
Developers plan next stage of $100m masterplanned community
Developers have lodged an application for Stage 4 of a $100 million masterplanned community that will house 500 residents in Brisbane‘s north. Summerlin Estate at Banyo is expected to house about 500 residents in a mix of 206 townhouses and apartments when completed in about five years. Stage one of six was completed in 2017.…
Magnolia Residences, Summerlin Banyo – March Construction Update – 2020
MARCH 2020 We are pleased to announce that since our last update the following milestones were achieved: • After a full week of dry weather, the ground was dry for the driveway to be poured. • Most fence/lot divisions are now in place with the remainder underway and expected to be completed shortly. • Landscaping…
Magnolia Residences, Summerlin Banyo – Construction Update – February 2020
FEBRUARY 2020 We are pleased to announce that since our last update the following milestones were achieved: • Final works are underway for the building and preparation for certification has commenced • Preparation for plan sealing has commenced • Storage cages have been installed in the basement • Landscape works for the street frontage have…
Magnolia Residences, Summerlin Banyo – Construction Update – November 2019
November 2019 We are pleased to announce that in the last month the following milestones were achieved: • Externally, rendering and painting has been completed to the building with scaffold having been removed to most of the building. External fire stairs and access ways are currently under construction. • Internally, tiling, joinery and painting is…