We are pleased to bring you the construction update for our latest stages.
Lilly Residences
• Recent wet weather has severely hampered construction for the months of February and March
therefore the forecast settlement date has been adjusted to mid-2022.
• During the last couple of weeks however we have been able to install some of the pad footings and the tower crane.
• Work scheduled for the next month includes:
o Completion of the pad footings and all basement columns
o Construction of basement walls and main slab
Terrace Homes Stage 7
• Recent wet weather has severely hampered construction for the months of February and March
therefore the forecast settlement date has been adjusted to December 2021.
• In between rain events we have been able to complete all under slab plumbing works.
• One building slab has been poured with others prepped ready for concrete this week.
• The installation of the timber frames has commenced.
• Work scheduled for the next month includes:
o Completion of the pad footings and all basement columns
o Construction of basement walls and main slab
Book an inspection now to view our display apartment,
open by appointment only 7 days a week.
Call 1800 461 860 to arrange your inspection today.