Summerlin Banyo – Construction Update – September 2021

TERRACE HOMES – STAGE 7 SOLD OUT

We are pleased to bring you the next construction update.

  • External works commenced in September with carports, driveways and roads being poured.
  • Internally, stairs have been installed and kitchen, bathroom and laundry cabinetry is being installed.
  • Fix-out (skirtings and architraves) continues and is complete to approximately. 70% of dwellings.
  • Waterproofing and tiling to wet areas has commenced.

Practical building completion of the Terraces Homes should be completed by mid-November.