Lilly Residences
We are pleased to bring you the construction update for our latest stages.
- The installation of services in the basement are practically complete.
- On the ground level internal wall framing is complete and electrical and plumbing rough ins are nearing completion.
- Level one remains a no-go zone as it is still full of formwork bracing the level two slab.
- The level two slab was poured on the 17th September.
- Blockwork and formwork are progressing on level two in preparation for the level three pour which is scheduled for mid-October.
The forecast settlement date has not changed. It is still scheduled to occur mid-2022.