August 2019
The construction crew at Summerlin is working hard and we have achieved the following milestones in the last month:
• On the ground level, all window frames have been installed and all units have now been sheeted with Gyprock. Kitchen and bathroom cabinets have been delivered.
• Level one has wall partitions installed and plumbing, electrical and air conditioning rough ins are complete. Window frames have been installed and gyprock lining is starting.
• Level two has wall partitions installed with electrical and plumbing rough ins underway.
• The third level slab has been poured and blockwork is complete. The roof frame has been installed with battens and roof sheets due to be installed early next week.
We are pleased to advise that delivery of the Central Community Facilities (including the park area and pool) has been brought forward. Works commenced during the month of July with the view to have the facility open for residents prior to Christmas.
If you have already chosen to call Summerlin home, it won’t be long before we’ll be making you feel welcome. In the meantime, please be aware, Magnolia Residences remains a construction site and not for public access.