Summerlin Banyo – Construction Update – November 2021

Lilly Residences The installation of services in the basement are complete. On the ground level internal wall framing is complete, electrical, mechanical and plumbing rough ins are complete. Level one has formwork removed, with minimal prop jacks in place for the level two slab. Framing is practically complete with service rough ins underway. Level two […]